The five line items that quietly eat your margin — the implied scope behind work you already quoted. Here's each one, and how to stop giving it away.

The scope you'd price — with the implied work caught before it becomes a change order.

Five that cost the most

Not exotic — just the hard, implied scope that follows from work you already quoted. Miss them at bid time and they come back as change orders, callbacks, or margin you gave away.

If you scope

Relocating a fixture

What quietly drops off: the drain + vent reroute and the plumbing permit.

Moving the sink, toilet, or tub moves its drain and vent — and code caps how far the trap arm can run to the vent, so it's real pipe plus an inspection, not a reconnect in place.

Written as "move the vanity," it reads like an hour of labor. The reroute and permit become a change order you absorb or awkwardly re-bill.

IPC · trap-arm limit
If you scope

Opening up a wall

What quietly drops off: a load-bearing check — and if it bears, an engineer-sized beam, posts to the foundation, and a permit.

If the wall carries load there's no rule of thumb: it needs a stamped beam and a load path all the way down to the footing.

Priced as demo and patch, a bearing wall turns into engineering, steel or LVL, and framing that never made it onto the bid.

IRC · structural
If you scope

A new tiled shower

What quietly drops off: an A118.10 waterproofing membrane and a pan sloped to the drain.

Tile and backer board don't waterproof — the membrane does, and the water that gets past the tile has to reach the drain.

Leave the system off the scope and it's either unbilled, or it comes back as a callback and a tear-out behind finished tile.

ANSI A118.10
If you scope

Grab bars "down the road"

What quietly drops off: solid in-wall blocking at grab-bar heights — now, while the walls are open.

A grab bar has to hold 250 lb, which means wood blocking behind the tile. Nearly free today; a demolition job once the wall is closed.

Skip it and the eventual install means opening finished walls — a cost someone eats, and it reads as a planning miss.

ANSI A117.1
If you scope

Demo in a pre-1978 home

What quietly drops off: lead-safe RRP practices — assume or test, a certified firm, containment.

The EPA presumes pre-1978 paint is lead unless it's tested, so disturbing it triggers lead-safe work rules.

Containment, certified labor, and cleanup verification are their own line items. Unscoped, they're margin — or a fine.

EPA · RRP

If you're thinking…

"I already have a process."
Good — this doesn't replace it. It's a second set of eyes on the implied scope your checklist assumes you'll remember, every item tied back to code.
"My clients won't sit through it."
There's no sit-down. It's your own walkthrough — you talk through the space the way you already walk it, and the scope builds as you go.
"It won't know my trade."
It's built on the trades' own codes, and every suggestion ties back to something you actually said — never a blanket checklist bolted onto the room.

See them on your own walkthrough

Start a free walkthrough: talk through one space and watch the scope build — implied items flagged, grounded in code, before you price it.

Start a free walkthrough

No login, no card, nothing to install — you're building a real scope in your browser.

Grounded in the trades' own codes
NECIPCIRCNFPA 54ANSI A118.10ANSI A117.1EPA RRP